GPU Capacity Management

Simulated planning

Run:ai-style analytics · Fleet headroom · NVIDIA GPU demand planning

Total capacity

512

64 NVIDIA GPU workers

Allocated capacity

389

76.0% of physical capacity

Available capacity

123

102 healthy schedulable · 21 blocked

GPU utilization

70.4%

Inventory snapshot · weighted average

Demand scenario

Demand grows 10% every 30 days; reserve 15% of healthy capacity. Existing allocations on unhealthy workers remain in demand.

30-day forecast

430GPUs demanded

0 GPU fleet shortfall

Plan 48 additional GPUs

Model-specific reserve · 8-GPU node increments

60-day forecast

474GPUs demanded

0 GPU fleet shortfall

Plan 88 additional GPUs

Model-specific reserve · 8-GPU node increments

90-day forecast

520GPUs demanded

40 GPU fleet shortfall

Plan 144 additional GPUs

Model-specific reserve · 8-GPU node increments

Historical GPU utilization · last 90 days

Historical allocation and forecast demand

NVIDIA GPU capacity by model

ModelTotalAllocatedAvailableHealthy free30d demand60d demand90d demandReserve breach
NVIDIA B3001601204037132146160Day 24
NVIDIA H2001281002820111122134Day 7
NVIDIA H1001281002818111122134Already breached
NVIDIA L40S96692727768492Day 53

When additional NVIDIA GPUs may be required

NVIDIA B300

Plan now

40 additional GPUs · 5 worker nodes for the 90-day horizon

Demand exceeds the 15% reserve target in 24 days. With a 30-day lead time, initiate planning now.

Restore 8 GPUs on unhealthy workers before committing to new hardware.

Validate workload pipeline, reclaim idle reservations, and assess MIG/consolidation before procurement. GPU models are not interchangeable.

NVIDIA H200

Plan now

40 additional GPUs · 5 worker nodes for the 90-day horizon

Demand exceeds the 15% reserve target in 7 days. With a 30-day lead time, initiate planning now.

Restore 8 GPUs on unhealthy workers before committing to new hardware.

Validate workload pipeline, reclaim idle reservations, and assess MIG/consolidation before procurement. GPU models are not interchangeable.

NVIDIA H100

Plan now

48 additional GPUs · 6 worker nodes for the 90-day horizon

Demand exceeds the 15% reserve target today. With a 30-day lead time, initiate planning now.

Restore 16 GPUs on unhealthy workers before committing to new hardware.

Validate workload pipeline, reclaim idle reservations, and assess MIG/consolidation before procurement. GPU models are not interchangeable.

NVIDIA L40S

Plan by day 23

16 additional GPUs · 2 worker nodes for the 90-day horizon

Demand exceeds the 15% reserve target in 53 days. With a 30-day lead time, initiate planning by day 23.

Validate workload pipeline, reclaim idle reservations, and assess MIG/consolidation before procurement. GPU models are not interchangeable.

Historical utilization and growth are illustrative, not collected Run:ai analytics. Forecast = current model allocations × (1 + 30-day growth)^(days / 30). Expansion restores the reserve on healthy capacity, rounded per model to 8-GPU workers; no inventory, quota, or deployment is changed.